Angel Parkway Expansion (FM 2551)

Managing Agency

Texas Department of Transportation (TxDOT)

The TxDOT Dallas District plans, designs, builds, operates, and maintains the state transportation system in the following counties:  Collin, Dallas, Denton, Ellis, Kaufman, Navarro and Rockwall.  The TxDOT Collin County Area Office led by Area Engineer Jennifer Vorster, PE, is responsible for all TxDOT work within Collin County.

Contact Information

TxDOT Collin County Area Office                Jennifer Vorster, PE        972-542-2345        [email protected]

City of Allen Project Manager                        Chris Flanigan                  214-509-4576        [email protected]

TxDOT Control Section Job (CSJ) Number: 20561042

More details are also available online at the TxDOT Project Tracker by following this link: TxDOT Project Tracker

Background Information

The Angel Parkway project is an expansion project of the existing two-lane roadway to a six-lane roadway. Originally planned to be an expansion to a four-lane roadway, the improved six-lane format will provide better transportation across the western edge of the City of Lucas. The roadway borders the major commercial center in Lucas and runs 3.4 miles south on the west side of Lucas, connecting Estates Parkway to Parker Road (FM 2514) and the City of Murphy, where it will be realigned with Hogge Drive / North Murphy Road. TxDOT began this widening project as a result of the commuting traffic demands in the area, including from the City of Allen, City of Parker, and the City of Murphy.

Upon completion, the new roadway will have dedicated turning lanes and allow for better flow of traffic to the roads and shopping centers it connects.  Construction for this project is being conducted by Harper Brothers Construction LLC. Texas Department of Transportation (TxDOT) has estimated that the project will be completed in early 2026. More updates will be provided on this page as the project moves forward.

Project Area

Project Updates

January 2024

  • Drainage items are being installed, utilities being relocated, and the right of way (ROW) is being cleared.

November 2023

  • Construction work begins at the location.

March 2019

  • Design is completed. Work to begin regarding utility and right-of-way coordination.

August 2015

  • Project design phase begins.

Project Funding

Project Funding - TxDOT Connect

Estimated Project Cost: $65,817,000

Expenditures

  • Project Engineering: $1,491,294.05
  • Construction: $2,857,948.14
  • Construction Engineering: $65,475.79
  • Total: $4,414,717.98

Last Updated: April 17, 2024