The typical process for an inspection of a single family dwelling is:
- Plumbing rough and gas – The form board survey will be provided at this stage. Roll-off dumpster, erosion control, and t-pole construction fence are required.
- Slab and foundation – Foundation must pass pre-pour inspections by the City and by the builder’s foundation engineer prior to pouring. Slab and foundation plans must be on site at time of inspection.
- Frame – This includes building, plumbing, electrical, and mechanical roughs.
- Temporary utility – Electric and gas meters released.
- Culvert and approach
- Reports required at final inspection to obtain a Certificate of Occupancy (C/O):
- Septic Tank Approval from Collin County
- Fire and Irrigation Backflow Reports (if system installed)
- Foundation Letter stating the engineer has completed the pre-pour inspection
- Grading for water flow on lot
- Energy Report (Compliance Report for Certificate of Occupancy in compliance with N1105.4.2.2 (R405.4.2.2) of the IECC)
- Termite Report
- Water Meter Inspection