Roadway, Water, and Construction Projects
===========================================================
ROADWAY PROJECTS
WEST LUCAS ROAD WIDENING
Update – September 26, 2022
Status – Design
Designer – BCC Engineering
Contractor – TBD
2019 Budget – $12,550,000
Design Cost – TBD
Construction Cost – TBD
From – Angel Parkway
To – Country Club Road
West Lucas Road Proposed Improvements
WATERWORKS PROJECTS
BAIT SHOP INTERSECTION WATERLINE RELOCATIONS
Update – April 18, 2023
Status – Construction
Designer – Huitt-Zollars
Location – Lucas Road/Southview Drive Intersection
Contractor – J&L Construction
Design Cost – $98,875.00
Construction Cost – $1,184,318.00
Total Cost – $1,283,193.00
As part of the TxDOT FM 1378/FM 3286 (aka Bait Shop) Intersection project, the City of Lucas will need to relocate 3,000+/- linear feet of 12-inch waterlines: Section A) 1,900 LF from Edgefield Lane to Prado Verde Drive along W. Lucas Road and Southview Drive and Section B) 1,100 LF from Southview Drive to Lost Valley Drive along E. Lucas Road.
DRAINAGE PROJECTS
ORCHARD ROAD SOUTH CULVERT AND CHANNEL IMPROVEMENTS
Update – April 18, 2023
Status – Construction
Designer – Birkhoff, Hendricks and Carter, LLP
Location – Orchard Road
Contractor – J&L Construction
Design Cost – $32,450.00
Construction Cost – $347,038.00
Total Cost – $379,488.00
RIMROCKS DETENTION POND EMBANKMENT IMPROVEMENTS
Update – April 18, 2023
Status – Construction
Designer – Birkhoff, Hendricks and Carter, LLP
Location – East side of Rimrocks development in alignment with channel under Orchard Road
Contractor – G-Rod Construction
Design Cost – $23,280.00
Construction Cost – $164,870.00
Total Cost – $188,150.00
TEXAS DEPARTMENT OF TRANSPORTATION (TxDOT) PROJECTS
TxDOT - Bait Shop (FM 1378/FM 3286) Intersection
Update – January 7, 2021
Status – Design
Budget – $4,000,000 to $5,000,000
CSJ: 1392-01-044
Schedule (Per City Staff)
2018-2020 – Environmental Work
2020-2021 – Design Work
May 2023 – Construction Starts
2025 – Construction Ends
Some folks in Lucas refer to this intersection (Lucas Road/Southview Drive) as the intersection by the Bait Shop.
TxDOT - Angel Parkway (FM 2551)
From Estates Parkway
To Parker Road
Update – January 7, 2021
Status – Utility Relocation
Budget – $11.5 Million
CSJ: 2056-01-042
July 2022 – Construction Starts
Reconstruct and widen from two lane to six lane divided
TxDOT - Estates Parkway (FM 2170) Safety Enhancements
From - Angel Parkway
To - Country Club Road
CSJ: 1392-01-048
Status - Pre-Construction
Schedule:
Construction Starts – January 2023
Construction Ends – September 2023